CONSTRUCTION India

Real estate builder: projects back on schedule, and costs back under control

INDUSTRY
Construction and real estate development
LOCATION
Kozhikode, Kerala, India
ENGAGEMENT
6 months
FOCUS
Project control, site management, procurement, stage billing
85% of project milestones now met on schedule, up from 50%
30% less material wastage on site
₹ 45 lakh saved per project
8 weeks to the first measurable gain

The challenge

The company was building several residential projects at once, each with its own site team, contractors and suppliers. Demand was good, but every project ran late. Costs crept past budget, and buyers kept calling to ask when they would get their keys.

Site engineers spent their days firefighting. Materials were ordered in a rush and at a premium, and the cash from stage payments came in later than it should have. The company had 4 projects under way, about 320 apartments in all. Projects were running an average of 7 months late, with cost overruns of around 12%.

What we found

We walked every site, sat in on contractor meetings, and compared planned and actual progress, cost and cash for each project, putting a rupee value on each gap.

  1. 01
    Sites had no working plan.There was a master schedule on paper, but no weekly look-ahead that crews and contractors worked to. Only half of planned monthly milestones were met, and idle labour and equipment cost about ₹ 6 lakh a month.
  2. 02
    Purchasing was reactive.Materials were bought when a site ran short, at higher prices, with wastage and pilferage nobody measured. Emergency purchases cost 8 to 10% above normal rates. Material wastage ran at about 7% against a norm of 3%, roughly ₹ 18 lakh per project.
  3. 03
    Stage billing lagged the work.Buyers were invoiced weeks after each stage was finished, so the company funded construction out of its own pocket. Stage invoices went out 3 to 4 weeks late, keeping about ₹ 2.5 crore tied up at any time.

What we built

Across the layers of the Organise to Grow model.

01 Operating model Clear roles for project manager, site engineer, quantity surveyor and purchasing, with authority levels and hand-offs between site and office.
02 Operating backbone A master schedule with a weekly look-ahead for every site, material planning against the schedule, a cost-to-complete report and a stage-billing tracker.
03 Daily management rhythm A daily site huddle, a weekly progress and cost review for each project, and a monthly review across the whole portfolio.
04 People and leadership Site engineers coached to plan ahead, run the reviews and answer for schedule and cost.

The results

Every project now has a plan that the site actually works to. Materials arrive when they are needed, cost overruns are visible early enough to act on, and stage invoices go out as soon as each stage is complete. Milestones met rose from 50% to 85% and material wastage fell 30%. Cost overruns came down from 12% to 4%, and stage invoices now go out within 3 days of completion.